RAB PLAN REVISI







LAMPIRAN I









RENCANA ANGGARAN BIAYA PEKERJAAN PENGEMBANGAN & PERENOVASIAN MASJID AL-ITTIHAD BINONG PERMAI
TANGERANG – BANTEN















No. Jenis Pekerjaan Volume Hrg Satuan Hrg Jumlah
(Rp) (Rp)
1.0. PEKERJAAN PERSIAPAN
1.1 Ruang Bouwplank / pengukuran M2 256 35,000 8,960,000
1.2 Pembersihan puing-puing M3 LS 8,000,000
T O T A L
2.0. PEKERJAAN GALIAN & URUGAN
2.1 Galian tanah / Pondasi Tapak M3 220 30,000 6,600,000
2.2 Urugan tanah kembali . M3 66 20,000 1,320,000
2.4 Urugan pasir urugan bawah lantai T.10 cm M3 32 210,000 6,720,000
2.5 Pemadatan Stemper m3 260 10,000 2,600,000
2.6 Bongkar Bagunan lama LS 20,000,000 20,000,000
T O T A L
3.0. PEKERJAAN PONDASI DINDING
3.1 Pasang pondasi M3 240 25,000 6,000,000
3.2 Pasang dinding bata 1 : 5 M3 960 40,000 38,400,000
T O T A L
4.0. PEKERJAAN GALIAN & URUGAN
4.1 Sloop beton M3 22.5 2,000,000 45,000,000
4.2 Kolom beton (STT + Praktis) M3 23.6 2,000,000 47,200,000
4.3 Balok beton M3 32.5 2,000,000 65,000,000
4.5 List plang beton M3 10 2,000,000 20,000,000
T O T A L
5.0. PEKERJAAN PLESTER
5.1 Plesteran dinding M3 3072 30,000 92,160,000
SUB T O T A L
6.0. PEKERJAAN ATAP COR - TOP DEK
6.1 Sloop Pembalokan Atas M3 22.5 2,000,000 45,000,000
6.2 Rangka Wire Dek batang 65000 500 32,500,000
6.3 Limiditer Dek Atap Kaso 6/8 batang 290 45,000 13,050,000
6.4 Triplek M2 60 90,000 5,400,000
6.5 Kawat Kg 20 16,500 330,000
6.6 Hotmix M3 35.5 620,000 22,010,000
6.7 List plang M3 48 100,000 4,800,000
T O T A L
7.0. PEKERJAAN JENDELA/ALUMINIUM
1.1 Paket Kusen Jendela Aluminium Pcs 26 650,000 16,900,000
T O T A L
8.0. PEKERJAAN RANGKA PLAFON
8.1 Pekerjaan rangka plafon M3 768 35,000 26,880,000
8.2 Pasang triplek 768 40,000 30,720,000
8.3 Pasang list kayu plafon 1536 10,000 15,360,000
T O T A L
PEKERJAAN KUBAH
1.1 Paket Kubah Rangka Besi 25,000,000
9.0. PEKERJAAN LANTAI
9.1 Pasang lantai keramik 40 x 40cm M3 185 60,000 11,100,000
9.2 Pasang lantai Teras Granite 80x80cm 35 120,000 4,200,000
9.3 Pasang Lantai Tempat Wudhu/KM 30x30cm 22 50,000 1,100,000
9.4 Keramik Dinding KM/Temptt Wudhu 18 50,000 900,000
T O T A L
10.0. PEKERJAAN PENGECATAN
10.1 Pengecatan dinding & plafon M3 3072 15,000 46,080,000
10.2 Pengecatan Kubah 108 20,000 2,160,000
T O T A L
11.0. PEKERJAAN SANI TAIR
11.1 Pasang closet jongkok Buah 2 300,000 600,000
11.2 Pasang bak fiber 2 150,000 300,000
11.4 Pasang kran air 20 100,000 2,000,000
T O T A L
12.0. PEKERJAAN INSTALASI AIR & LISTRIK
12.1 Saluran pembuangan air kotor / air hujan M 40 100,000 4,000,000
Pekerjaan saluran air kotor 0
12.3 Bak Tampung 2 600,000 1,200,000
12.4 Pembuatan spiteng & rembesan 1 2,500,000 2,500,000
12.5 Instalasi istrik titik lampu,sakelar,grounding,box panel) 40titik 270,000 10,000,000
PEKERJAAN RAILING GATE
1.1 Paket Railing
besi flat 0.5/3. M3 0.32 450,000 14,400,000
PEKeRJAAN TURAP / EDGING SUNGAI
1.1 Pekerjaan Perataan dan pemadatan edge sungai M3 0.32/100 250,000 8,900,000
1.2 Pondasi batu kali 1.3 M3 120 55,000 7,500,000
1.3 Pembesian O/ 12 Batang 50/12 65,000 4,000,000
1.4 Pembesian O/ 8 Batang 80/12 55,000 4,400,000
1.5 Instalasi Pengaliran Air sungai/PVC Pcs 12-3"/4 60,000 720,000
1.6 Pembetonan M3 120/3.5 300,000 36,000,000
T O T A L
T O T A L K E S E L U R U H A N
D I B U L A T K A N 767,970,000

RAB - Pembangunan Masjid Al-Ittihad

LAMPIRAN I









RENCANA ANGGARAN BIAYA PEKERJAAN PENGEMBANGAN & PERENOVASIAN MASJID AL-ITTIHAD BINONG PERMAI
TANGERANG – BANTEN















No. Jenis Pekerjaan Volume Hrg Satuan Hrg Jumlah
(Rp) (Rp)
1.0. PEKERJAAN PERSIAPAN
1.1 Ruang Bouwplank / pengukuran M2 256 35,000 8,960,000
1.2 Pembersihan puing-puing M3 LS 8,000,000
T O T A L
2.0. PEKERJAAN GALIAN & URUGAN
2.1 Galian tanah / Pondasi Tapak M3 220 30,000 6,600,000
2.2 Urugan tanah kembali . M3 66 20,000 1,320,000
2.4 Urugan pasir urugan bawah lantai T.10 cm M3 32 210,000 6,720,000
2.5 Pemadatan Stemper m3 260 10,000 2,600,000
2.6 Bongkar Bagunan lama LS 20,000,000 20,000,000
T O T A L
3.0. PEKERJAAN PONDASI DINDING
3.1 Pasang pondasi M3 240 25,000 6,000,000
3.2 Pasang dinding bata 1 : 5 M3 960 40,000 38,400,000
T O T A L
4.0. PEKERJAAN GALIAN & URUGAN
4.1 Sloop beton M3 22.5 2,000,000 45,000,000
4.2 Kolom beton (STT + Praktis) M3 23.6 2,000,000 47,200,000
4.3 Balok beton M3 32.5 2,000,000 65,000,000
4.5 List plang beton M3 10 2,000,000 20,000,000
T O T A L
5.0. PEKERJAAN PLESTER
5.1 Plesteran dinding M3 3072 30,000 92,160,000
SUB T O T A L
6.0. PEKERJAAN ATAP COR - TOP DEK
6.1 Sloop Pembalokan Atas M3 22.5 2,000,000 45,000,000
6.2 Rangka Wire Dek batang 65000 500 32,500,000
6.3 Limiditer Dek Atap Kaso 6/8 batang 290 45,000 13,050,000
6.4 Triplek M2 60 90,000 5,400,000
6.5 Kawat Kg 20 16,500 330,000
6.6 Hotmix M3 35.5 620,000 22,010,000
6.7 List plang M3 48 100,000 4,800,000
T O T A L
7.0. PEKERJAAN JENDELA/ALUMINIUM
1.1 Paket Kusen Jendela Aluminium Pcs 26 650,000 16,900,000
T O T A L
8.0. PEKERJAAN RANGKA PLAFON
8.1 Pekerjaan rangka plafon M3 768 35,000 26,880,000
8.2 Pasang triplek 768 40,000 30,720,000
8.3 Pasang list kayu plafon 1536 10,000 15,360,000
T O T A L
PEKERJAAN KUBAH
1.1 Paket Kubah Rangka Besi 25,000,000
9.0. PEKERJAAN LANTAI
9.1 Pasang lantai keramik 40 x 40cm M3 185 60,000 11,100,000
9.2 Pasang lantai Teras Granite 80x80cm 35 120,000 4,200,000
9.3 Pasang Lantai Tempat Wudhu/KM 30x30cm 22 50,000 1,100,000
9.4 Keramik Dinding KM/Temptt Wudhu 18 50,000 900,000
T O T A L
10.0. PEKERJAAN PENGECATAN
10.1 Pengecatan dinding & plafon M3 3072 15,000 46,080,000
10.2 Pengecatan Kubah 108 20,000 2,160,000
T O T A L
11.0. PEKERJAAN SANI TAIR
11.1 Pasang closet jongkok Buah 2 300,000 600,000
11.2 Pasang bak fiber 2 150,000 300,000
11.4 Pasang kran air 20 100,000 2,000,000
T O T A L
12.0. PEKERJAAN INSTALASI AIR & LISTRIK
12.1 Saluran pembuangan air kotor / air hujan M 40 100,000 4,000,000
Pekerjaan saluran air kotor 0
12.3 Bak Tampung 2 600,000 1,200,000
12.4 Pembuatan spiteng & rembesan 1 2,500,000 2,500,000
12.5 Instalasi istrik titik lampu,sakelar,grounding,box panel) 40titik 270,000 10,000,000
PEKERJAAN RAILING GATE
1.1 Paket Railing
besi flat 0.5/3. M3 0.32 450,000 14,400,000
PEKeRJAAN TURAP / EDGING SUNGAI
1.1 Pekerjaan Perataan dan pemadatan edge sungai M3 0.32/100 250,000 8,900,000
1.2 Pondasi batu kali 1.3 M3 120 55,000 7,500,000
1.3 Pembesian O/ 12 Batang 50/12 65,000 4,000,000
1.4 Pembesian O/ 8 Batang 80/12 55,000 4,400,000
1.5 Instalasi Pengaliran Air sungai/PVC Pcs 12-3"/4 60,000 720,000
1.6 Pembetonan M3 120/3.5 300,000 36,000,000
T O T A L
T O T A L K E S E L U R U H A N
D I B U L A T K A N 767,970,000